Microsoft East Wenatchee Data Center 30 Day Public Comment Period Sept. 17, 2024 - Oct. 17, 2024

This is a 30-day public comment period for the review of Microsoft East Wenatchee Data Center's draft permit, technical support document, and notice of construction (NOC) application with associated documents. Comment Period is September 17, 2024, 12:00 a.m. through October 17, 2024, 11:59 p.m.

 

Microsoft is proposing to expand its existing data center in East Wenatchee. Microsoft proposes to construct and operate two more data centers (EAT06, and EAT09) at 875 Urban Industrial Way, in East Wenatchee. The new data centers will include an additional 20 3.0-MWe generators and 2 0.5-MWe generators. 


The 20 3.0‑MWe generators will meet state and federal emission standards. They will be equipped with:

  • Passive catalyzed diesel particulate filters
  • Selective catalytic reduction to reduce emissions

 

We determined this proposal satisfies the requirements of Chapter 173-400 WAC.

 

The public is invited to comment.

 

View project documents online.

 

Comment period ends Thursday, October 17, 2024, 11:59 p.m.




Contact Information

*Indicates Required Fields

Submitted by Value

First Name

Last Name

Address

City

State

ZIP

Email

Your Comment


Please enter your comments in the "Insert comments" space below. To submit attachments, use the "Upload a File" button. Then hit "Continue" to review your comments.
 
To submit comments for a group, please visit our Commenting Tips webpage.
 
Next steps:
After the public period ends, we will:
  • Review and respond to comments.
  • Issue the air permit.

 
Contact information is necessary if you want to receive future notices or responses related to this topic.



*Uploading a file is optional*

You may attach up to five 20 MB files to accompany your submission. Allowed formats are pdf, jpg, jpeg, png, txt, gif, doc, docx, xlsx, xls. If you experience technical difficulties submitting your comment please contact the person listed at the bottom of this page.


Thank you for subscribing to the Microsoft East Wenatchee Data Center 30 Day Public Comment Period Sept. 17, 2024 - Oct. 17, 2024 mailing list.